Extension of time EOT in construction contracts

Clock.jpg

Contents

[edit] What is an extension of time?

Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).

Mechanisms allowing extensions of time are not simply for the contractor's benefit. If there was no such mechanism and a delay occurred which was not the contractor's fault, then the contractor would no longer be required to complete the works by the completion date and would only then have to complete the works in a 'reasonable' time, and the client would lose any right to liquidated damages.

[edit] How is an extension of time granted?

When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.

[edit] What types of delays might allow an extension of time?

Relevant events that might allow an extension of time may include:

The contractor is required to prevent or mitigate the delay and any resulting loss, even where the fault is not their own.

[edit] How are claims for extension of time assessed?

Assessing claims for an extension of time can be complicated and controversial. There may be multiple or concurrent delays, some of which are the contractor's fault and some not. There are many occasions where contractors contribute to delay themselves by their performance during design periods, when producing drawings, mock ups and samples or in interfacing with sub-contractors.

In North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744, the Court of Appeal confirmed that parties are free to agree contract clauses which exclude any entitlement to an extension of time where a contractor-caused delay occurs concurrently with a relevant event, and that such clauses do not offend the prevention principle. This means the specific wording of the extension of time provisions in a contract needs to be checked carefully, as they may displace the more general common law approach to concurrent delay.

Crucial in assessing applications for extension of time is the quality of the information provided and records available. For more information, see How to prepare a claim for an extension of time.

Claims should be judged against the actual progress of the works, not the programme, and must demonstrate the link between the breach (cause) and the delay.

The contract administrator may review extensions of time after practical completion and further adjust the completion date.

Claims for extension of time can run alongside claims for loss and expense (relevant matters); however, one need not necessarily lead to the other.

It is very important when deducting liquidated damages to ensure that the correct contractual procedures are adhered to. In the case of Octoesse LLP v Trak Special Projects Ltd [2016], Justice Jefford held that Octoesse was not entitled to deduct liquidated damages as they had agreed to an extension of time after a certificate of non completion had been issued. The JCT Intermediate Building Contract is constructed such that:

'If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Architect/Contract administrator shall issue a certificate to that effect. If an extension of time is made after the issue of such certificate, the extension shall cancel that certificate and the Architect/Contract Administrator shall where necessary issue a further certificate.'

As Octoesse had not issued a further certificate of non completion, they were not entitled to deduct liquidated damages.

To find out more, see Octoesse LLP v Trak Special Projects Ltd.

[edit] Related articles on Designing Buildings

[edit] External references

Comments

[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.


Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again